Completed · Aug 2024Built from Laagna 140 Coastal
Family home in Pirita
Об этом проекте
142 m² total area Завершено Aug 2024 Построено в 6 months Класс энергоэффективности A Доверие 92 · Gold
Где
Pirita, Tallinn
Kloostrimetsa tee 41 · Pirita, Tallinn · Harju County, Estonia
Как это было построено
Хронология строительства
1
Design freeze
Feb 2024
2
Factory production
Mar – May 2024
3
Foundation on site
Apr 2024
4
Shell assembly
8 days · Jun 2024
5
Move-in
Nov 2024
Total contract-to-keys: 27 weeks. Reported by the manufacturer and confirmed by the owners; Jem.house has not independently verified individual milestone dates.
Как построено
Характеристики проекта
Прочее
Climate zoneCoastal Baltic · 4b
Energy classA
FoundationInsulated slab
CladdingVertical thermowood
RoofStanding-seam zinc
HeatingAir-water heat pump
От владельцев
Отзыв владельца
KL
“The factory production timeline was off by a single day across six months. The crew that came to the site already knew our soil report by heart. Two winters in and we have not seen condensation on a single window.Kaarel & Liisa Tamm · Owners · moved in November 2024