Completed · Aug 2024Built from Laagna 140 Coastal

Family home in Pirita

Pirita, Tallinn, Harju County, Estoniabuilt by Põhjala Kodud142 Verified by Jem.house

Об этом проекте

142 total area Завершено Aug 2024 Построено в 6 months Класс энергоэффективности A Доверие 92 · Gold
Где

Pirita, Tallinn

Kloostrimetsa tee 41 · Pirita, Tallinn · Harju County, Estonia
Open in Google Maps
Как это было построено

Хронология строительства

1
Design freeze
Feb 2024
2
Factory production
Mar – May 2024
3
Foundation on site
Apr 2024
4
Shell assembly
8 days · Jun 2024
5
Move-in
Nov 2024

Total contract-to-keys: 27 weeks. Reported by the manufacturer and confirmed by the owners; Jem.house has not independently verified individual milestone dates.

Как построено

Характеристики проекта

Прочее

Climate zoneCoastal Baltic · 4b
Energy classA
FoundationInsulated slab
CladdingVertical thermowood
RoofStanding-seam zinc
HeatingAir-water heat pump
От владельцев

Отзыв владельца

KL
The factory production timeline was off by a single day across six months. The crew that came to the site already knew our soil report by heart. Two winters in and we have not seen condensation on a single window.
Kaarel & Liisa Tamm · Owners · moved in November 2024
В процессе и завершено

Фотографии строительства и готового объекта

Скоро

Построено

Põhjala Kodud
Tartu, EstoniaС 2011340 completed projects 4.8 · 142 reviews Доверие 92 · Gold
View profile

Больше проектов от Põhjala Kodud

Projects / Põhjala Kodud
Completed · Aug 2024
Family home in Pirita
Pirita, Tallinnby Põhjala Kodud
142Built in 6 months

Где

Kloostrimetsa tee 41
Pirita, Tallinn

Хронология строительства

1
Design freeze
Feb 2024
2
Factory production
Mar – May 2024
3
Foundation on site
Apr 2024
4
Shell assembly
8 days · Jun 2024
5
Move-in
Nov 2024
Как построено

Характеристики проекта

Прочее

Climate zoneCoastal Baltic · 4b
Energy classA
FoundationInsulated slab
CladdingVertical thermowood
RoofStanding-seam zinc
HeatingAir-water heat pump

Отзыв владельца

The factory production timeline was off by a single day across six months. The crew that came to the site already knew our soil report by heart. Two winters in and we have not seen condensation on a single window.Kaarel & Liisa Tamm · Owners · moved in November 2024

Фотографии строительства

Скоро

Построено

Põhjala Kodud
Tartu · since 2011 · Доверие 92

Об этом строительстве

Завершено
Aug 2024
Продолжительность строительства
6 months
Общая площадь
142 m²
Заявленный бюджет
€268,000
Климатическая зона
Coastal Baltic · 4b
Класс энергоэффективности
A
Владельцы
Family of five · Moved from a 1970s panel flat
LAAGNA 140 COASTAL